CompTIA Project+ Practice Test 2 PK0-003

CompTIA Project+ Practice Test 2 PK0-003

The sponsor informs the project manager that something else needs to be added to the scope statement in the execution phase. The project manager should

 

 

 

 

A project manager conducted a risk probability assessment this happened during

 

 

 

 

A sponsor has authorized the project manager for an new  project. He put it in writing. What would be key element in this document?

 

 

 

 

The reason for  a post-project review is

 

 

 

 

Which tool would be used to decompose a project?

 

 

 

 

HR has concerns regarding the work ethic of a team member. The project manager should give them

 

 

 

 

In status meeting a positive project risk is identified that can be controlled. You should

 

 

 

 

The budget is $200,000 is in month #9 and it has an earned value of $180,000 and actual costs of $190,000. The cost variance is:

 

 

 

 

Which risk response strategies involves the use of insurance, performance, bonds, or warranties?a

 

 

 

 

The project manager is most senior in which organizational structures?

 

 

 

 


Question 1 of 10