CompTIA Project+ Practice Test 1 PK0-003

CompTIA Project+ Practice Test 1 PK0-003

The critical path of the network diagram is

 

 

 

 

A project has EV of $5,000 and cost of $6,000. What is the CPI?

 

 

 

 

Final project acceptance requirements are found in the

 

 

 

 

The deadline to respond to the RFP has expired while still in the execution phase. . You should then

 

 

 

 

As the project manager you should formally close a project when

 

 

 

 

Transition plans involve

 

 

 

 

A project manager determines the trends a process is exhibiting she used

 

 

 

 

The project is 50% complete. The project plan was up to 10 months, 150 gadgets ($55 each) per month. The total budget is $9,000. The value of the project is

 

 

 

 

_________________Will decrease the effect of a project threat

 

 

 

 

What does SOW stand for?

 

 

 

 


Question 1 of 10