CompTIA Project+ Practice Test 1 PK0-003 CompTIA Project+ Practice Test 1 PK0-003 What does SOW stand for? a. Sponsor of Work b. Statement of Work c. Systematic Organizational Work d. Solid Operational Workflow Final project acceptance requirements are found in the a. Project Transition plan b. Project scope document c. Project charter d. Project quality plan A project has EV of $5,000 and cost of $6,000. What is the CPI? a. 1000 b. 183 c. 1.2 d. 0.83 The critical path of the network diagram is a. Start-D-B-Finish b. Start-D-E-F-Finish c. Start-C-E-Finish d. Start-A-Z-Finish Transition plans involve a. Project warranty b. Project reports c. Project structure d. Project workflow A project manager determines the trends a process is exhibiting she used a. Pareto chart b. RACI chart c. Gantt chart d. Run chart As the project manager you should formally close a project when a. When KPI is 56 b. When another more valuable project is available c. It has been terminated unexpectedly d. CPI is 1.5 half way through The project is 50% complete. The project plan was up to 10 months, 150 gadgets ($55 each) per month. The total budget is $9,000. The value of the project is a. $5500 b. $4500 c. $2500 d. $9000 The deadline to respond to the RFP has expired while still in the execution phase. . You should then a. Monte Carlo analysis b. Evaluate and choose a seller response. c. Find a new vendor d. Find a buyer _________________Will decrease the effect of a project threat a. Risk Migration b. Risk Mitigation c. Risk classification d. Risk diversification Loading … Question 1 of 10